Terna Faces 100 GW of Data Center Grid Requests in Italy as CEO Warns of Speculative Demand

Terna says nearly 600 data center projects in Italy have requested over 100 GW of grid connections, far exceeding what the country can realistically build.

RD

Research Desk

14 October 2026 · 1 min read

Terna Faces 100 GW of Data Center Grid Requests in Italy as CEO Warns of Speculative Demand

Italy's grid operator Terna has logged connection requests for nearly 600 data centre projects exceeding 100 GW in total, a volume that chief executive Pasqualino Monti says surpasses what the country can realistically build.

A warning from the grid operator

Speaking on Wednesday at an event hosted by business school RCS Academy, Monti cautioned that the requests "far exceed the real capacity to implement the projects." Italy's task, he argued, is to back the sector's expansion "efficiently and gradually" rather than chase every application.

Applications have more than doubled in a year

The current tally represents a sharp acceleration. In May 2025, connection requests to Terna stood at 42 GW. In just over a year, the requested capacity has more than doubled, a sign of how quickly developers and investors are seeking to stake out positions in the Italian data centre market.

Where Italy's data centres sit today

The country operates roughly 205 data centres, concentrated mainly in the northern region of Lombardy. Milan alone accounts for 68% of national data centre power capacity, according to the Data Center Observatory at Milan's Politecnico University.

The Observatory also estimates the city attracts 23% of announced data centre investments across Europe, placing it among the industry's leading European hubs.

Confirmed investment through 2028

The pipeline of actual projects continues to grow alongside the surge in applications. Politecnico's Data Center Observatory expects 83 new data centre projects in Italy through 2028, representing up to USD 28 billion in investment.

Taken together, the nearly 600 requests exceeding 100 GW and the USD 28 billion project pipeline illustrate both the magnitude of interest in Italian data centre capacity and the distance between announced ambitions and what may ultimately be delivered, the very gap Monti's remarks sought to underline.

Tagged

Data centre grid connection requestsTernaItaly data centre marketspeculative capacity pipeline

Live from the tracker

The projects behind these stories

Capacity, capex, stage, contractors and verified contacts for every project we track, updated daily.

Data Center Development / JC3 Campus – Jakarta, Indonesia · Not disclosed · On-going / Under Construction SBE - Ports Technology Campus Redevelopment · Ohio, United States · Not disclosed · On-going / Under Construction FA/TTU - Project Matador AI Data Center Campus · Texas, United States · Not disclosed · Pre-Construction GS - Donghae Data Center · Gangwon-do, South Korea · 2,400 MW · Pre-Construction NUAI - Lea County Data Center · New Mexico, United States · 7,000 MW · Planning SACIII - Berry Hill Data Center · Virginia, United States · 299 MW · Planning OLV/MCG - Wonder Valley Alberta Data Center · Alberta, Canada · Not disclosed · Design PD - Heartland Industrial Park Data Center Campus · Indiana, United States · Not disclosed · On-going / Under Construction BAM/NEE - Paducah Data Center · Kentucky, United States · 4,600 MW · Planning META/BOC - Richland Parish Data Center Campus · Louisiana, United States · 5,000 MW · On-going / Under Construction Data Center Development / JC3 Campus – Jakarta, Indonesia · Not disclosed · On-going / Under Construction SBE - Ports Technology Campus Redevelopment · Ohio, United States · Not disclosed · On-going / Under Construction FA/TTU - Project Matador AI Data Center Campus · Texas, United States · Not disclosed · Pre-Construction GS - Donghae Data Center · Gangwon-do, South Korea · 2,400 MW · Pre-Construction NUAI - Lea County Data Center · New Mexico, United States · 7,000 MW · Planning SACIII - Berry Hill Data Center · Virginia, United States · 299 MW · Planning OLV/MCG - Wonder Valley Alberta Data Center · Alberta, Canada · Not disclosed · Design PD - Heartland Industrial Park Data Center Campus · Indiana, United States · Not disclosed · On-going / Under Construction BAM/NEE - Paducah Data Center · Kentucky, United States · 4,600 MW · Planning META/BOC - Richland Parish Data Center Campus · Louisiana, United States · 5,000 MW · On-going / Under Construction