Tract Plans $13.11 Billion Data Center Campus in Stockton-on-Tees, UK, Amid Local Opposition
Tract unveils £10bn Stockton-on-Tees data center campus: 13 buildings, grid funding pledge, 2027 construction start amid 6,000-signature petition.
Research Desk
Colorado-based data center park developer Tract has unveiled proposals for a 13-building technology campus on farmland at the western edge of Stockton-on-Tees in northeast England, an investment that could exceed USD 13.11 billion and that has already triggered a community backlash led by the local member of parliament.
Site location and proposed development plans
The site earmarked for the proposed Stockton-on-Tees Technology Park lies west of Middlesbrough, bounded by Darlington Back Lane to the north and Yarm Back Lane to the east. As well as up to 13 data center buildings, the plans include an on-site substation.
Tract revealed the proposals this week and described the location as well-suited to data center requirements, citing its proximity to Norton substation.
Grid funding pledge and delivery schedule
Detailed information about the scheme has not yet been released, but Tract has signaled that more than USD 13.11 billion could be invested in the development.
The company intends to lodge a planning application with the local council in December 2026, and if consent is granted, construction could begin in 2027, with the buildings delivered in phases over the subsequent 11 years.
To support the power demands of the campus, Tract has committed to paying significant amounts of capital to National Grid to fund the additional grid infrastructure the project requires, with the company stating this will protect local bill payers.
Community resistance and the brownfield debate
The proposal has attracted considerable opposition from residents. A petition launched by Stockton West MP Matt Vickers opposing the development has gathered more than 6,000 signatures.
"More than 6,000 people have now signed my petition, sending a clear message that residents do not want to see our countryside swallowed up by this development," the Conservative MP said.
"I want to see new jobs and investment coming to Stockton, but that should not come at the expense of our precious green spaces when there are brownfield alternatives available. Once our farmland is built on, it's gone for good. I will continue to stand alongside residents, fight these proposals, and press the Council to prioritize brownfield sites."
Tract has pushed back on the criticism, saying it examined brownfield sites across the Tees Valley but did not identify one in Stockton that satisfied all of its development requirements.
Second UK scheme follows County Durham plans
The Stockton project is Tract's second venture in the UK. Earlier in November the company announced a large-scale campus in County Durham, roughly 20 miles north of the Stockton proposal.
The Durham Technology Park could accommodate up to seven data center buildings with a combined capacity of 500 MW, together with an on-site substation. Tract likewise plans to submit the Durham planning application to the local council in December 2026.
Tract was founded by former Cologix CEO Grant van Rooyen and describes itself as a developer of master-planned data center parks. Its business model involves preparing sites so that they are zoned, powered, and shovel-ready for other companies to then construct data centers on.
After launching in Nevada in 2023, the company has set out plans for large-scale campuses in several US states, among them Texas, Virginia, Arizona, Minnesota, Iowa, Illinois, North Carolina, and Utah.
Tract's parent company, Tract Capital, also controls a dedicated data center developer called Fleet DC, which will build on land owned by Tract as well as on other sites.
Northeast England's expanding data center footprint
Although the northeast of England has not historically ranked among the UK's primary data center hubs, the region has experienced a surge of activity in recent years. QTS is building a large campus north of Newcastle near Blyth, while UK operator Latos is developing a campus in the Stockton-on-Tees area.
The locality also contains existing digital infrastructure. Lumen has previously operated a former Level 3 facility in Middlesbrough, and Stratus Technologies, now known as Unity, ran a facility in the area. UK fiber operator CityFibre maintains a two-cabin fiber exchange in Stockton near Grangefield Academy on Oxbridge Avenue.
Elsewhere in the wider region, a 48 MW data center campus received planning approval from Redcar & Cleveland Council in 2023 on a former chemicals plant site, though it is not known whether construction has started.
A large data center development at the Teesworks brownfield site near Middlesbrough also secured planning approval last year, a project to which Google has reportedly been linked. In addition, Semcorp and Digital Reef are planning a large-scale campus in Teesside.